"Fourteen five" the latest progress of major construction projects! Yuhang this cloud computing data center is nearing completion

In May this year, the Provincial Development and Reform Commission issued the "Zhejiang major construction projects" Fourteen five "project list" Yuhang multiple items selected.

In these major construction projects in the Yuhang, Liangzhu Jiang laboratories and laboratories have been put into use in the construction of the project is to speed up construction, which Zhejiang Alibaba Cloud Computing Data Center Union and the project will be completed by December this year!

Zhejiang Alibaba Cloud Computing Data Center Union and projects

As from the Alibaba Group in Hangzhou headquarters closest data center, Alibaba Zhejiang cloud computing Renhe data center will be integrated application Ali Dharma homes, flat head brother of the latest research results, achieved in the data center scale, calculate the force, energy, intelligence, etc. comprehensive upgrade. Renhe data center deployment of the world’s largest liquid-cooled clusters, to achieve the world’s most advanced level.

▲ project renderings

Project Profile: Zhejiang Alibaba Cloud Computing Data Center Union and projects located in Hangzhou Qianjiang Economic Development Zone, with a total land area of ??about 142 acres, the construction of the data center room, integrated space, power distribution room and other production and auxiliary buildings 120,000 square meters purchase standard rack 5100, servers, gateways, load balancing and other mechanical and electrical equipment 10 million, and Ali cloud related to product placement to the appropriate device. After the completion of Yuhang District will inject new impetus to the development of industrial clustering of large data fusion applications. Time is the project started in October 2018, planned completion time is December 2021, a project was put into operation in December 2020, the second phase is expected to put into operation in time for the June 2022.

Project Progress: At present, A, B, C, H building was completed, D test validation floor, E building mechanical and electrical construction.

The progress of other major construction projects, take a look!

Ali Baba Dharma Institute of South Lake Park

South Lake Hospital Dharma project will carry scientific and technological innovation as the industrial city of the future Alibaba and technological proving ground, the Southlake Regional Hospital and South Lake Dharma build a future source of technology, the future of the industry and lead to a model city of the future, the big data computing , AI algorithms, chip count forces, unmanned, in areas such as quantum computing research and development, and actively support the "digital Zhejiang", and to work closely with enterprises in the region, university institutions, innovation networks and the formation of industrial clusters, leading the region collaborative technological innovation.

▲ project renderings

Project Description: The project is located in the future science and technology city of South Lake Science Center Area, with a total land area of ??342.12 acres, with a total investment of 2.144 billion yuan, with a total construction area of ??490,500 square meters, the proposed research and development office, science laboratory, ancillary services and other functions space. Construction unit to preach Ka Technology (Hangzhou) Co., Ltd. Time is the project started in October 2020, the anticipated completion date is May 2023, it is expected to put into operation in time for the December 2023.

Project progress: The project is currently underway earthwork and construction of basement structures.

Zhejiang University centrifugal gravity simulation and experimental project

The project is included in the "major national scientific and technological infrastructure" Thirteen Five "plan", the project will build the world’s largest capacity centrifugal gravity simulation and experimental equipment, centrifugal acceleration and load controlled adjustable centrifuge capacity of 1900 acceleration of gravity. T, the maximum centrifugal acceleration of 1500 times the gravitational acceleration, the maximum load of 32 tons.

▲ project renderings

Project Description: The project is located in the city of the future of science and technology, with a total land area of ??about 89 acres, with a total investment of about 21 billion yuan, with a total construction area of ??34,560 square meters, the main construction of two gravity centrifuge host six gravity JEM and related facilities . Construction unit of Zhejiang University. Start time for the project in February 2020, the anticipated completion date is December 2024, will be launched in June 2025.

Project progress: ongoing basis construction equipment, it has been the host machine and heavy machine-compartment model machine room floor the first floor slab construction is completed; complete the construction shallow pit crown beam support beams.

AI vivo global R & D center project

After completion of the project as artificial intelligence vivo global research and development headquarters, engineering cloud base algorithm research and development of major mobile phone AI algorithms, AI technical capabilities, the ability to recommend the search algorithm, cloud AI training / Mystery platform, a new generation of information technology to achieve high-end chain AI artificial Intelligence gathering field of artificial intelligence research and development to create new heights.

▲ project renderings

Project Description: The project is located in the former warehouse Street, with a total land area of ??about 53.8 acres, a total construction area of ??323,000 square meters. The total investment of 21.5 billion yuan, the construction unit for the Weaver mobile communications (Hangzhou) Co., Ltd. Start time for the project in November 2020, planned completion time for the December 2024, it is expected to put into operation in time for the June 2025.

Project progress: pile foundation works completed, the first, two stays completed, the third channel support 90% complete.

In addition to these project-specific landing Yuhang, Yuhang District still more major construction projects across the province administrative regions "Fourteen five" project to assume the role of backbone, including the characteristics of the provincial town of technological innovation projects in major categories, modern intelligent transformation projects of industrial enterprises and other major industrial categories.

Yuhang will promote major projects to speed up the landing, speed up construction, and strive to play a major construction project for sustainable growth effective investment, the role of stone ballast quality of economic and social development.